摘要 核电厂与常规火电厂在建设程序上是有差别的,其中差别之一是国家对核电厂实行核安全许可制度,在核电厂建设的全过程中,核安全监管的强力部门有五次介入,这是我国核安全监管的基点。本文根据《中华人民共和国民用核设施安全监督管理条例》(国务院1996年发布,以下简称条例)和《条例实施细则之一:核电厂安全许可证件的申请和颁发》的主要内容,对核电厂建设全过程中有关核安全许可制度的许可事项、需提交的文件、审评重点、审评依据进行简要的叙述。 The nuclear power plant and conventional thermoelectric power station are difference in the construction program, one of the differences is the country implements the nuclear safety licensing system to the nuclear power plant, in the entire process of nuclear power plant construction, the force department of nuclear safety supervising and managing has five involvements, this is our country nuclear safety supervising and managing basic point. This article according to the primary coverage of “ the People's Republic of China Civilian Nuclear Installations Safety Monitor and Management Ordinance” (issued in 1996 by the State Council, hereafter referred to as ordinance) and “ one implementation instruction of the ordinance : The application and issues of nuclear power plant safety permission credential” , introduce permission item, constructs the document, must submit key, the appraisal basis carties, the appraisal to the nuclear power plant which in the entire process the related nucleus safe licensing system.
作者 康慧 王正
出处 《电力勘测设计》 2007年第4期73-76,共4页 Electric Power Survey & Design
关键词 强力部门 厂址选择 建造 运行 force department selection of plant site construction operation
  • 相关文献

同被引文献7

引证文献5

二级引证文献10

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部