废热锅炉多级给水泵的问题及处理

Troubleshooting of multi-stage feed water pump for waste heat boiler
下载PDF
导出
摘要 针对硫磺制酸装置废热锅炉多级给水泵在运行过程中存在的设备振动大、部件磨损严重,因而运行周期短等问题,对平衡装置进行受力分析,并在实际检修过程中采取相应的措施,取得了良好的效果。泵运行周期从20天延长到2年,为主装置的稳定运行提供了有力的保证。 A force analysis was conducted on the balance devices of multi-stage feed water pumps for waste heat boiler of a sulphur-burning sulphuric acid plant, due to occurrence of troubles, such as strong vibration during rotating, serious wearing of balance disk and ring and consequently, shortened service life. Some measures were taken in actual maintenance and good results obtained. The pump service life was increased from 20 days to 2 years, giving a solid assurance for stable operation of main plant.
作者 郑亚琼
出处 《硫酸工业》 CAS 2007年第4期40-43,共4页 Sulphuric Acid Industry
关键词 多级泵 锅炉给水泵 问题 力分析 措施 multi-stage feed water pump waste heat boiler troubleshooting force analysis measure
  • 相关文献

参考文献2

  • 1化工厂机械手册.化工厂机械手册编辑委员会编,维护检修常用基础资料(一)[M].北京:化学工业出版社.1991.1343-1346.
  • 2化工机械制造工艺与安装修理.南京化学工业公司化工学校等合编,楼宇新主编[M].北京:化学工业出版社,1981.338-339.

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部