根据梨园煤矿三水平地质条件和现有生产系统情况,对三水平原设计进行分析,找出不科学、不合理的问题,并进行了优化设计,最大限度地回收了煤炭资源,提高了生产能力。
According to the third level geological conditions and the curreet production system situation of Liyuan Coal Mine, make an analysis on the original design for the third level, try to find out the unscientific and irration problems, and make optimum design, as a result, reclaim the coal resource and raise the productive capacity.
出处
《煤炭技术》
CAS
2007年第9期59-61,共3页
Coal Technology
关键词
矿井
水平
地质条件
生产系统
mine
level
geological condition
production system