摘要
国家电网公司750kv示范工程系统调试范围为750kv官亭变电站变电工程、750kV兰州东变电站变电工程、750kV官亭变电站至750kV兰州东变电站一条140km的750kV线路。系统调试方案包括两部分:第一部分为750kV输变电示范工程系统调试方案.第二部分为750kV示范工程系统调试测试方案。本文详细叙述了系统调试方案中的试验项目和试验内容:并对系统调试测试项目进行了简单介绍。对系统调试结果进行了简单概括分析,并给出了系统调试结论。
The 750 kV transmission pilot project system commissioning test in Northwest of China included GuanTing 750 kV transmission substation, LanZhouDong transmission substation and 750 kV transmission line of 140 km. The contents of 750 kV system commissioning test were divided into two parts. The first part was the 750 kV system commissioning test program, and the second part was the 750 kV system commissioning measurement scheme. The system commissioning test program including test items and test contents were introduced in this paper. The system commissioning measurement scheme was briefly introduced. The results of system commissioning test were briefly analyzed. The conclusions were given in the end.
作者
杨万开
史可琴
范越
万筱钟
牛拴保
印永华
YANG Wan-kai,SHI Ke-qin,FAN Yue, WAN Xiao-zhong, NIU Shuan-bao,YIN Yong-hua( 1.China Electric Power Research Institute, Beijing 100085,China; 2.Northwest China Grid Company, Xi'an 710048, China)
关键词
750
KV示范工程
系统调试方案
系统调试测试方案
系统调试
750 kV transmission pilot project
System commissioning test program
System commissioning measurement scheme
System commissioning test