摘要
西霞院水电站是小浪底水利枢纽的反调节配套工程,厂用电源的引接方式要满足厂用负荷的安全运行,特别是防汛电源的可靠运行,同时也要考虑设备布置方便。设计比较了5个技术方案,最终选取了一个相对完善的方案。
Xixiayuan Hydropower Staion is the re-regulating project of Xiaolangdi Hydtopower Project, considering the safety requirement of service power, especially in flood season, and layout convenience of switchgears, five tapping forms from generator exit circuit are compared and the best one is selected.
出处
《湖北水力发电》
2007年第5期25-27,共3页
Hubei Water Power
关键词
西霞院水电站
厂用电源
引接方式
Xixiayuan Hydropower Station
service power
tapping form