摘要
龙羊至乌兰330 kV线路在龙羊侧安装了3台330 kV单相电抗器,投运初期含气量增长较快,直接影响设备运行的安全可靠性,经过2004年6月进行设备改造后,至今含气量正常。文章对这一过程进行了分析,对处理情况进行了介绍。
The Longyang side of Longyang- Wulan 330 kV transmission line installs three 330 kV single - phase reactors, the gas content is increasing comparatively fast in initial operation stage, and has directly influenced the equipment operation's safety reliability. After the equipment reconstruction on J une,2004,the containing gas content is normal up to now. The paper makes analysis on the reconstruction process and introduces the treatment methods.
出处
《青海电力》
2007年第3期43-45,53,共4页
Qinghai Electric Power
关键词
电抗器
含气量
超标
分析
reactor
gas content
over specification
analysis