摘要
文章针对3G项目启动后对通信大楼油机供电需求的增长,导致部分大楼油机容量不足的情况,探讨利用电源负载错峰管理方式,合理化分配油机容量,达到不增加油机配置实现安全供电的目的。
This article is aim at the situation of part of diesel engine in the telecommunication building lack of capability cased by the increase powering needs of telecommunication building after the 3G proiect start-up. It discuss the reasonable assigning the capability of diesel engine by the management method of stagger the load peak value to realize the goal of safety powering without increase any diesel engine.
出处
《通信电源技术》
2007年第5期85-86,共2页
Telecom Power Technology
关键词
错峰
油机
3G
分时
限流
stagger the load peak value
diesel engine
3G
time-sharing
current limit