依据《1000kV架空送电线路施工及验收规范》Q/GDW153-2006和《1000kV架空输电线路张力架线施工工艺导则》Q/GDW154-2006的有关规定,在全面分析总结500kV超高压输电线路紧线、附件施工工艺的基础上,针对1000kV架空输电线路设计结构的特点,对紧线、附件施工工艺进行了深入研究,提出了特高压紧线、附件施工工艺。对规范特高压线路紧线、附件施工工艺,保证工程质量将起到一定的积极作用。
According to the Regulation of 1 000 kV Overhead Transmission Line Construction and Acceptance (Q/GDW153-2006) and the Guidance of 1 000 kV Overhead Transmission Line Tension Stringing Technics (Q/GDW154-2006), and on the basis of analyzing and summarizing of 500 kV EHV transmission line take-up and accessory construction technics, the take-up and accessory construction technics are studied considering the characteristics of 1 000 kV overhead transmission line structures, and recommended take-up and accessory construction technics are presented. It plays an active role in standardizing UHV line take-up and accessory construction technics, as well as ensuring construction quality.
出处
《电力建设》
2007年第10期24-29,32,共7页
Electric Power Construction
关键词
特高压
架空输电线路
紧线附件
工艺研究
UHV
overhead transmission line
take-up accessory
study of technics