东台500kV变电站是为了满足福州电网负荷快速增长和省会城市对供电质量的要求而建设,在设计中对设备选型进行了多方案比选、对配电装置布置方案进行设计优化,在精细化、人性化设计上下功夫,以期达到尽善尽美。
The Dongtai 500 kV substation is built to meet load increase of Fuzhou grid and power quality requirements of capital city. In the design process, multiple schemes for equipment selection are compared, distribution device configurations are optimized, and many efforts have been put into fine and humanistic designs to reach perfection.
出处
《电力建设》
2007年第10期36-39,共4页
Electric Power Construction
关键词
变电站
主接线
设备选型
配电装置
创优设计
substation
main wiring
equipment selection
distribution device