一种求解项目调度中资源均衡问题的粒子群算法 被引量:4

Particle Swarm Algorithm for Solving Resource Leveling Problem in Project Scheduling
下载PDF
导出
摘要 针对资源受限下的项目资源均衡问题的自身特点,及其与传统资源受限项目调度问题的相似之处,设计了一种以优先值法作为粒子表达RLP问题的粒子群优化算法。选用并行进度生成机制,同时在将资源均衡转化成资源受限下项目调度问题的过程中,根据资源均衡本身的特点,对并行进度生成机制进行处理。最后结合算例进行仿真实验,验证了构建的资源均衡模型以及粒子群算法求解资源均衡问题的可行性。 Through analyzing similarities and differences between the resource constrained project leveling problem(RLP) and resource constrained project scheduling problem, a particle swarm optimization algorithm (PSO) is developed :priority- based representation determined the way of particle; parallel schedule methods was taken as schedule generation scheme, and in concurrent when RLP was transformed to RCPSP. A disposal is made to Parallel SGS based on RLP' characteristic Finally , a case simulation on the model and algorithm is made proved the validity of the RLP model and PSO algorithm is proved by the simulation.
出处 《科学技术与工程》 2007年第22期5805-5809,共5页 Science Technology and Engineering
基金 国家自然科学基金(70671037) 高等学校博士学科点专项科研基金(20050532005)资助
关键词 资源平衡 优先值 粒子群算法 并行进度生成机制 resource leveling priority-based representation particle swarm algorithm parallel schedule generation scheme
  • 相关文献

参考文献8

  • 1[1]Leu Sousen,Yang Chunghuei,Hang Jiunching.Resource leveling in construction by genetic algorithm-based optimization and its decision support system application.Automation in Construction.2000; 10:27-41
  • 2[2]Neumann K,Zimmermann J.Resource leveling for projects with schedule-dependent time windows.European Journal of Operational Research,1999; 117:591-605
  • 3刘士新,王梦光,唐加福.一种求解资源受限工程调度问题的遗传算法[J].系统工程学报,2002,17(1):1-7. 被引量:30
  • 4刘士新,王梦光,唐加福.求解项目调度中资源水平问题的近似算法[J].系统工程学报,2002,17(4):296-302. 被引量:13
  • 5[5]Brucker P,Drexl A,Mohring R,et al.Resource-const rained project scheduling:Notation,classification,models,and method.European Journal of Operational Research,1999; (112):3-41
  • 6谢晓锋,张文俊,杨之廉.微粒群算法综述[J].控制与决策,2003,18(2):129-134. 被引量:422
  • 7[8]Zhang Hong,Li Xiaodong,Li Heng,et al.Particle swarm optimization-based schemes for resource-constrained project scheduling.Automation in Construction.2005; (14):393-404
  • 8[9]Kolisch R.Serial and parallel resource-constrained project scheduling methods revisited:Theory and computation.European Journal of Operational Research,1996; (90):320-333

二级参考文献39

  • 1王梦光,刘士新.资源受限工程调度问题的最新发展[J].控制与决策,1996,11(A01):105-112. 被引量:11
  • 2刘士新.资源受限工程调度问题的优化方法研究[M].沈阳:东北大学,2000..
  • 3[31]Eberhart R, Hu Xiaohui. Human tremor analysis using particle swarm optimization[A]. Proc of the Congress on Evolutionary Computation[C].Washington,1999.1927-1930.
  • 4[32]Yoshida H, Kawata K, Fukuyama Y, et al. A particle swarm optimization for reactive power and voltage control considering voltage security assessment[J]. Trans of the Institute of Electrical Engineers ofJapan,1999,119-B(12):1462-1469.
  • 5[33]Eberhart R, Shi Yuhui. Tracking and optimizing dynamic systems with particle swarms[A]. Proc IEEE Int Conf on Evolutionary Computation[C].Hawaii,2001.94-100.
  • 6[34]Prigogine I. Order through Fluctuation: Self-organization and Social System[M]. London: Addison-Wesley,1976.
  • 7[1]Kennedy J, Eberhart R. Particle swarm optimization[A]. Proc IEEE Int Conf on Neural Networks[C].Perth,1995.1942-1948.
  • 8[2]Eberhart R, Kennedy J. A new optimizer using particle swarm theory[A]. Proc 6th Int Symposium on Micro Machine and Human Science[C].Nagoya,1995.39-43.
  • 9[3]Millonas M M. Swarms Phase Transition and Collective Intelligence[M]. MA: Addison Wesley, 1994.
  • 10[4]Wilson E O. Sociobiology: The New Synthesis[M]. MA: Belknap Press,1975.

共引文献459

同被引文献27

引证文献4

二级引证文献9

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部