东北世贸广场主楼基础底板属大体积防水混凝土结构,通过采取一系列控制大体积混凝土温度与裂缝的技术措施,系统组织浇筑施工、养护和监测,确保了该大体积混凝土结构的施工质量。
Foundation slab in main building of Northeast World Trade Plaza is a rare structure of mass waterproof concrete. A series of technical measurements have been done to control the temperature of mass concrete and cracks. At the same time, scientific construction, maintenance and monitoring ensure the quality of the mass concrete structure.
出处
《施工技术》
CAS
北大核心
2007年第10期50-52,共3页
Construction Technology
关键词
大体积混凝土
裂缝控制
施工组织
mass concrete
crack control,
construction organization