通过介绍几种给水泵组常规的布置形式,提出了绥中发电厂二期工程的推荐方案——2台50%的汽动给水泵。然后从几个方面论述不设备用泵、采用本方案的可行性。
Through introduction to the layout of some ordinary feed - water pump sets, a proposal is given to Suizhong Power Plant 's second term project:two 50% turbine driven feedwater pumps. The feasibility of this design is detailed in several aspects.
出处
《水利电力机械》
2007年第10期30-33,共4页
Water Conservancy & Electric Power Machinery
关键词
1
000MW机组
汽动给水泵
电动给水泵
1 000 MW unit, turbine driven feedwater pump, motor driven feedwater pump