超长钢筋混凝土底板的无缝施工 被引量:1

Joint-free construction of super long reinforced concrete floor
下载PDF
导出
摘要 本钢第二炼铁厂5×75 m2烧结机改造带冷平台及带冷机室工程的基础为大型混凝土箱体结构,施工中采用混凝土加入U型混凝土膨胀剂(UEA)等措施,取消了基础底板原设计的后浇带,基础底板一次连续浇筑完成,解决了超长大体积混凝土无缝施工的裂缝控制问题。 The foundations of straight cooler platform and straight cooler room for 5 ×75 m^2 sintering machine reconstruction project of Bensteel No. 2 iron making plant are of large concrete box structure, such measures as adding U - type concrete expansion agent in concrete were adopted, the post - cast strip which was originally designed for soleplate was abandoned, the sole plate was cast continuously for one time,and the cracking control problem for joint- free construction of super -long bulk concrete was solved.
作者 马文义 关兵
出处 《工程建设》 2007年第5期51-53,共3页 Engineering Construction
关键词 超长结构 膨胀混凝土 后浇带 裂缝 super long structure expansive concrete post-cast strip cracking