摘要 循环流化床锅炉协调控制,是CFB锅炉自动控制的难点。介绍了白马示范电站从法国ALSTOM公司引进的国内首台300 MW CFB锅炉机组协调控制系统的各子系统组成,简述了外置床的加入对复杂耦合参数解耦所起的作用及在300 MW CFB锅炉调试期间的经验和体会。 Coordinated control system (CCS) of circulating fluidized bed combustion boiler is one of the difficulties in automatic control of CFB boiler. The configuration of each subsystem of CCS is briefly introduced according to the first 300 MW CFB boiler in Sichuan Baima Demonstration Substation, which is imported from ALSTOM of France. The effect of adding external bed on decoupling of the complicated coupling parameter is described as well as the experiences during the commissioning of 300 MW CFB boiler.
出处 《四川电力技术》 2007年第5期72-74,89,共4页 Sichuan Electric Power Technology
关键词 循环流化床锅炉 协调控制 外置床 解耦 circulating fluidized bed combustion boiler coordinated control external bed decoupling
  • 相关文献

参考文献3

  • 1熊天柱,田子平,李俊,缪正清,陈永国.循环流化床锅炉的大型化[J].锅炉技术,2004,35(2):1-6. 被引量:9
  • 2岑可法 倪明江.循环流化床锅炉理论设计与运行[M].北京:中国电力出版社,1997..
  • 3郑祖坤.循环流化床(CFB)锅炉控制策略[EB/OL].