摘要 研究了活动具有多种执行模式的项目支付进度安排问题,目的是寻求使项目收益最大化的支付进度包括支付事件,支付量以及与之相联系的活动执行模式和事件实现时间的安排.在对所研究问题进行界定的基础上,分别从承包商和业主两个角度构建了问题的非线性混合整数规划优化模型,并设计了由满意支付事件集合搜索模块和满意事件进度搜索模块构成的双模块模拟退火启发式求解算法.借助一个算例对研究进行了说明,结果表明:业主和承包商对支付进度安排的偏好差异明显;承包商的收益随着支付次数和支付比例的增加而上升,而业主正好相反;双方的收益均与折现率呈显著的负相关关系. This paper studies the project payment scheduling problem where activities may be performed with several modes. The objective is to find the payment schedule including payment event, payment amount, activity performing mode, and event realization time to maximize project profit. Based on the identification of the problem, two nonlinear mixed integer programming models are con- structed from contractor's and client's viewpoints respectively. A special simulated annealing heuristics which consists of the module seeking for the desirable payment event set and the module searching for the desirable event schedule is developed. The study's result is illustrated by using an instance and some conclusions are drawn: The client's preference on the payment schedule is obviously different from the contractor's; the latter's profit ascends with the increase of payment number and payment proportion and the reverse is true to the former; their profits drop with the augment of cash discount rate.
作者 何正文 徐渝
出处 《系统工程学报》 CSCD 北大核心 2007年第5期474-479,共6页 Journal of Systems Engineering
基金 国家社会科学基金资助项目(06CJY019) 陕西省软科学资助项目(2007KR56)
关键词 活动执行模式 项目支付进度安排 优化模型 双模块模拟退火启发式算法 performing mode of activity project payment scheduling optimal model two-module simulated annealing heuristics
  • 相关文献

参考文献14

  • 1Tavares L V. A review of the contribution of operational research to project management[ J ]. European Journal of Operational Research, 2002, 136 (1): 1--18 .
  • 2汪嘉旻,孙永广,吴宗鑫.净收益最大化的时间-费用交换问题研究[J].系统工程学报,2000,15(3):267-271. 被引量:8
  • 3Christenson C. Construction of present value tables for use in evaluation of capital investment opportunities [ J ]. The Accounting Review, 1995, 10(4): 666-673.
  • 4Herroelen W, Dommelen V, Demeulemeester E. Project network models with discounted cash flows : A guided tour through recent developments[ J]. European Journal of Operational Research, 1997, 100(1) : 97--121.
  • 5Dayanand N, Padman R. On payment schedules in contractor client negotiations in projects : An overview of the problem and research issues [ A ]. In: Weglarz J. Project Scheduling: Recent Models, Algorithms and Applications[ M ]. Boston: Kluwer Academic Publishers, 1999, 477--508.
  • 6Dayanand N, Padman R. On modeling progress payments in project networks[ J]. Journal of the Operational Research Society, 1997, 48(9): 906-918.
  • 7Dayanand N, Padman R. Project contracts and payments schedules: The client's problem[ J ]. Management Science, 2001, 47(12) : 1654--1667.
  • 8Dayanand N, Padman R. A two stage search heuristics for scheduling payments in projects [ J ]. Annals of Operation Research, 2001, 102(1): 197--220.
  • 9Ulusoy U, Cebelli S. An equitable approach to the payment scheduling problem in project management[ J]. European Journal of Operational Research, 2000, 127 (2) : 262--278.
  • 10Talbot B. Resource-constrained project scheduling with time-resource tradeoffs: The non-preemptive case[ J]. Management Science, 1982, 28(10) : 1197--1210.

二级参考文献8

共引文献41

同被引文献137

引证文献6

二级引证文献24

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...