摘要 察汗乌苏水电站工程大坝为目前国内在建的首座河床趾板建在深厚覆盖层上的百米级混凝土面板砂砾石坝。在大坝垫层区与主砂砾石区之间设置了必要的过渡区,就过渡料的生产,研究了洞挖料、洞挖料掺砂石骨料以及洞挖料掺配天然砂砾石料3个生产方案,最终采用洞挖料与天然冲洪积砂砾石料互掺的方式生产过渡料,获得了较好的技术经济指标。 The dam for the Chahanwusu Hydropower Station is the first concrete facing rockfill dam at 100 m level which is built in deep coverage at home. A transition zone is arranged between the dam cushion layer zone and main grit stone zone. For the production of transition materials, three production schemes of material from the excavation of tunnel, aggregate mixing with material from tunnel excavation, and natural grit stone material mixing with material from tunnel excavation were made. Finally, the transition material is produced from the natural grit stone material mixing with material from tunnel excavation, which gained good technical and economic indexes
出处 《水力发电》 北大核心 2007年第10期47-50,共4页 Water Power
关键词 面板坝 过渡料掺配 试验研究 察汗乌苏水电站 facing dam transition material mixture test and study Chahanwusu Hydropower Station
  • 相关文献

参考文献2

  • 1中国水利水电科学研究院.新疆察汗乌苏水电站面板坝过渡料补充试验报告[R].2006,4.
  • 2中国水电顾问集团西北勘测设计研究院.新疆察汗乌苏水电站工程可行性研究优化设计报告[R].2004,5.

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部