摘要 试桩静载试验目的,除JGJ94-94《建筑桩基技术规范》中规定要获取单桩极限承载力作为设计依据外,还应涵括获取试桩本身在成桩过程中的成功经验和数据(如锤击桩的终端贯入度,静压桩的终端压力值等)作为大量工程桩施工成桩过程及桩长终端控制的监理、施工、修改设计和验收的依据。这一论点是以10多年监理高层建筑工程锤击和静压钢筋砼预制桩为例,通过施工监理、施工实践、修改设计、竣工验收和业主使用多年全过程的实践论证得出的。 As the aim of pile test by the dead load method, except the stipulations on building pile technique standard for gaining single pile limit load as design foundation, we consider that ought to include obtaining the test pile' s various data while it is built, such as the end get-down degree of hammer pile or the end pressure of quiet pressing pile, etc. The data ought to become the part of basis of engineering pile in two aspects, one for the procedure control in forming pile, another for the end length control of pile. while the piles build in great quantity , the data ought to be used by the supervision, construction, adjusting the design and acceptance purpose. This opining comes from the hammer pile and the quiet pressing pile in practice building procedure for more than ten years.
出处 《江苏建筑》 2007年第5期41-42,58,共3页 Jiangsu Construction
关键词 锤击(静压)试桩静载试验目的 涵括 试桩成桩 贯入度(压力值) 单控 工程桩桩长施工监理依据 the aim of dead load test on hammer pile (quiet pressing pile) get-down degree of hammer pile pressure of quiet pressing pile single control the practical basis of the engineering pile in length
  • 相关文献

参考文献2

  • 1JGJ94-94建筑桩基技术规范[s].北京:中国建筑工业出版社.1995.
  • 2.GB50021-2001岩土工程勘察规范[S].北京:中国建筑工业出版社,2002..

共引文献79

同被引文献2

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部