期刊文献+

谈电力建设项目全过程跟踪审计的要点 被引量:2

Key Points of the Whole Process Tracking Audit of Power Construction Project
原文传递
导出
摘要 近几年来,由于电力供应紧缺,电力建设项目纷纷上马。站在审计监督的角度看,应当树立全过程控制的指导思想,"全面审计,突出重点"是审计工作中要落实的方针。审计中应把握立项、设计、施工、竣工、结算等各个阶段的特点,抓住重点,以点带面实施全过程跟踪审计,并通过审计人员认真细致的工作,客观公正、高质高效的审计服务,在电力建设项目管理方面取得良好的经济效益与社会效益。 In recent years, many power construction projects have been put into operation due to short electric power supply. From the perspective of audit supervision, such construction should be supervised and controlled throughout all its process, which is the guiding principle to be carried out in auditing, i.e., focusing on the main points while auditing from all aspects. Auditors should grasp the focal points of these projects throughout their whole processes including endorsing, designing, constructing, completing and settling account according to their different characteristics. By using the fruitful experience of one selected area to benefit all other areas, auditors should also track the whole auditing process with careful, industrious, objective and efficient work, and thus obtain excellent economic and social benefits in terms of power construction project management.
作者 阮伟龙
机构地区 南京工程学院
出处 《建筑经济》 北大核心 2007年第11期16-18,共3页 Construction Economy
关键词 电力建设项目 全过程审计 控制 power construction project the whole process audit control
  • 相关文献

参考文献3

  • 1姚梅炎,冯彬编著.投资项目审计工作手册[M].北京:中国物价出版社,2001.
  • 2刘钟莹,徐红.建筑工程造价与招投标[M].南京:东南大学出版社,2002.
  • 3尹贻林.工程造价与控制[M].北京:中国计划出版社,2003.

共引文献19

同被引文献4

引证文献2

二级引证文献2

相关作者