摘要
某工程利用框架结构特性,对托梁及待加固柱先利用体外索进行卸载,对托梁实施预应力加固处理以及增大柱子截面。针对高层结构托梁拔柱工程进行简化建模以提高非线性计算效率。
According to the character of the frame's structure, The external cable is used to unload the beam and the column, whick are needed reinforcement in this project. The joist is strengthened by pre-stressed steel and the pillar's section is increased. In order to enhance the efficiency of nonlinear computation ,the model is simplified in the project of supporting beam and removing column related to high structure.The practice indicates that, the unloading and its computation are reliable.
出处
《工程建设与设计》
2007年第11期40-42,共3页
Construction & Design for Engineering
关键词
托梁拔柱
预应力
可靠
加固
supporting beam and removing column
pre-stressed
reliable
strengthen