摘要
本文对由上海锅炉厂承制的泰山核电站300MW蒸汽发生器和稳压器的制造过程作了概述。重点介绍了制造设施、工艺试验及工艺评定,其中包括管板深孔加工、管子管板焊接以及管子管板胀管试验。
A brief description of the manufacturing process of the 300MWe steam generator and pressure stabiliser for Qinshan Nuclear Power Station in Shanghai Boiler Works is presented, with special emphasis on fabrication facilities, test procedures and technological evaluations during the manufacturing process-including deep drilling of tube-sheets, welding of tubes to tube-sheets and tube rolling tests.
出处
《动力工程》
CSCD
1989年第4期51-58,共8页
Power Engineering