以北京地铁十号线学院路站小月河桥桩加固工程为背景,论述了人工挖孔桩和洛阳铲探测管线技术、地面钻孔注浆加固桥桩的施工要点及主要参数,对类似工程有一定的参考价值。
Based on the background of No. 10 line Xueyuan Road Xiaoyuehe Bridge pile rdnforced project of Beijing subway, it discusses the construeting points and main parameters of artificial digging pile, Luoyang shovel-exploring skill and floor drilling pouring reinforced bridge pile. Therefore, it has a certain referring value for familiar projects.
出处
《山西建筑》
2007年第35期335-336,共2页
Shanxi Architecture
关键词
加固桥桩
注浆
洛阳铲
管线探测
地铁暗挖