二滩拱坝施工期改变浇筑层厚度加快施工的分析 被引量:2

Analysis of Ertan Arch Dam Lift Thickness Variation During Construction Period for Speeding up Construction
下载PDF
导出
摘要 为保证二滩水电站按期发电,在二滩拱坝施工期,承包商提出了改变大坝混凝土浇筑层厚度加快施工进度的计划,即浇筑层厚度由1.5m改为3.0m,并以聚乙烯冷却水管代替钢管。本文分析了改变浇筑层厚度的可行性、温控条件,温度徐变应力。实践证明,加快施工进度的方案是成功的。 n order to ensure that Ertan Hydropower Station generates power on time, during Ertan arch dam construction period,the contractor suggested to change the dam concrete lift thickness to speed up the construction progress,i, e. to change the lift thickness from 1.5m to 3.0m, and to use polyethylene cooling pipes instead of steel ones.In this paper feasibility of changing the lift thickness is studied,the temperature control conditions and temperature creep stresses are analysed. The construction practice demonstrates that the scheme for speeding up the construction is successful.
作者 陈秋华
出处 《水电站设计》 2007年第4期14-16,共3页 Design of Hydroelectric Power Station
关键词 砼拱坝 砼浇筑 浇筑层厚度 冷却水管 温度 徐变应力 二滩拱坝 concrete arch dam concrete placing concrete lift thickness cooling pipes temperature creep stresses Ertan arch dam
  • 相关文献

同被引文献18

引证文献2

二级引证文献21

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部