新乡电厂干煤棚工程网架高度高、跨度大,施工现场四周场地狭小,吊装机械无法展开。为此采用高空累积滑移法安装技术,满足了安全可靠的安装要求,并可确保电厂正常生产。
The dry coal shelter grid at Xinxiang Power Plant is high and large-spanned, while the narrow construction site makes it impossible to use hoisting equipment. Therefore, air accumulated sliding method was employed for its installation, not only satisfying the safety requirement of installation, but ensuring the normal production of the power plant.