期刊文献+

大型预应力排水渡槽结构设计的初步探讨 被引量:1

Tentative Approach to Structural Design of Large Pre-stress Drainage Aqueduct
下载PDF
导出
摘要 南水北调工程为了解决左岸排水问题,设计了大量的排水渡槽。排水渡槽常年处于无水状态,其实际工作环境与普通过水渡槽有很大区别。初步探讨了排水渡槽的结构设计,推导出了适用于排水渡槽的一种设计方法,并利用有限元软件对各个工况复合验算。最后通过模拟温度场,初步得出温度荷载对预应力排水渡槽结构受力有重要影响,为以后的相关设计提供参考依据。 In order to solve the drain question of the Left-Bank ,South-To-North Water Transfer Project design lots of drainage aqueduct. Drainage aqueduct is in the anhydrous state perennially, the actual working environment is greatly different with ordinary aqueduct. In this paper, the characteristics of the drainage Aqueduct , the section size and preliminary of pre-stressed tendons were first designed, and then using the finite ele- ment method to check the status of all workers. Finally, through simulating the temperature field, the temperature load have important implications on the pre-stressed drainage Aqueduct structure, this can provide reference method and basis for future design.
出处 《南水北调与水利科技》 CAS CSCD 2007年第6期110-113,共4页 South-to-North Water Transfers and Water Science & Technology
关键词 排水渡槽 预应力 设计方法 温度荷载 Drainage Aqueduct pre-stressed concrete design methods temperature load
  • 相关文献

参考文献5

二级参考文献11

  • 1赵顺波.南水北调大型钢筋混凝土多纵梁渡槽结构设计与试验研究(科研报告)[M].华北水利水电学院,1998..
  • 2E富马加利 蒋彭年等(译).静力学模型与地力学模型[M].北京:水利电力出版社,1979..
  • 3西北勘测设计研究院.SL/Tl91—96.水工混凝土结构设计规范.[M].北京:中国水利水电出版社,1997..
  • 4[1]河海大学,清华大学.水工钢筋混凝土结构学[M].中国水利水电出版社,2002.
  • 5赵顺波,南水北调大型钢筋混凝土多纵梁渡槽结构设计与试验研究(科研报告),1998年
  • 6朱以文,微机有限元前后处理系统Vizi CAD及其应用,1993年
  • 7王传志,钢筋混凝土结构理论,1985年
  • 8华东水利学院,水工设计手册.8,1984年
  • 9蒋彭年(译),静力学模型与地力学模型,1979年
  • 10赵瑜,赵平,李树瑶.大型预应力混凝土箱形渡槽结构三维有限元分析[J].长江科学院院报,1999,16(2):17-20. 被引量:31

共引文献142

同被引文献8

引证文献1

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部