资源强度可变的生产调度计划资源均衡分析

Analysis of Resource Leveling in Production Scheduling Problem with Changeable Resource Intensity
下载PDF
导出
摘要 在现代化加工制造过程中,通过制定合理的生产调度计划可以实现对资源的均衡利用。文章针对这类资源均衡问题,提出了一种新型的工序资源强度可变的资源均衡模型。该模型允许适当延长工序的工期来降低工序的资源强度,并引入工期延长率这一无量纲变量来表示工序工期所延长的程度。该变量使得模型中各工序间的时间约束在求解过程中能自动满足,从而避免非可行解的出现。该模型还兼容了工序资源强度不变的均衡模型的功能,并可以处理特殊工序资源强度不可变的要求。通过采用遗传算法对该模型进行求解,验证了其有效性。本文的模型可以广泛应用于生产调度管理、建设项目计划等领域,具有良好的应用价值。 In modem manufacturing process, resources can be utilized evenly by making a reasonable production schedule. A new kind of resource leveling model with changeable resource intensity is presented for solving this problem in this paper. Prolonging of activity durations is allowed in order to decrease resource inten- sity of activities in this model. A dimensionless variable named as duration prolonging rate is introduced to show the prolonged degree of activity duration. Time constraints among activities of a schedule can be automatically satisfied with the help of this variable during the whole computing process. Thus, infeasible solutions can be avoided. Moreover, the model can realize the same function as conventional models with unchangeable resource intensity and can fit the instance allowing unchangeable resource intensity of some special activities. Finally, the validity of the model in this paper is verified with the help of genetic algorithm. This model can be widely used in many fields such as management of production scheduling and network plan of construction project, which shows the application value of the model.
出处 《组合机床与自动化加工技术》 2007年第12期104-108,112,共6页 Modular Machine Tool & Automatic Manufacturing Technique
关键词 生产调度计划 资源均衡 遗传算法 工期延长率 production scheduling resource leveling genetic algorithm duration prolonging rate
  • 相关文献

参考文献9

  • 1Weng-Tat Chan, David K. H. Chua, Govindan Kannan. Construction resource scheduling with genetic algorithms [J]. Jounal of Construction Engineering and Management, 1996, 122 (2):125 - 132.
  • 2Kris G. Mattila, Dulcy M. Abraham. Resource Leveling of Linear Schedules Using Integer Linear Programming[J]. Journal of Construction Engineering and Management, 1998, 124 (3) :232 - 244.
  • 3Sou-Sen Leu, Chung-Huei Yang. GA-Based Multicriteria Optimal Model for Construction Scheduling [ J ]. Journal of Construction Engineering and Management, 1999,125 (6) :420 - 427.
  • 4Zne-Jung Lee, Chou-Yuan Lee. A hybrid search algorithm with heuristics for resource allocation problem [ J ]. Information Sciences, 2005,173 : 155 - 167.
  • 5陆惠民,杜训.工程项目资源优化的混合整数规划算法[J].东南大学学报(自然科学版),1991,21(4):123-129. 被引量:3
  • 6张连营,骆刚,鹿丽宁.遗传算法在工程项目资源优化中的应用[J].天津大学学报(自然科学与工程技术版),2001,34(2):188-192. 被引量:26
  • 7田军,寇纪淞,李敏强.利用遗传算法优化施工网络计划[J].系统工程理论与实践,1999,19(5):78-82. 被引量:33
  • 8杜黎.网络计划的资源优化和平衡[C].中国运筹学会.中国运筹学会第六届学术交流会论文集,中国运筹学会第六届学术交流会,湖南长沙,2000年10月10日-15日,香港:Global-Link出版社,2000:535-541.
  • 9罗时朋,王乘,杨彪.基于浮动工时率的资源均衡问题研究[J].华中科技大学学报(自然科学版),2003,31(3):78-80. 被引量:3

二级参考文献20

  • 1陈恩红,蔡庆生.约束满足问题的预处理方法研究[J].计算机科学,1994,21(5):38-41. 被引量:2
  • 2席裕庚,柴天佑,恽为民.遗传算法综述[J].控制理论与应用,1996,13(6):697-708. 被引量:346
  • 3胡应平.基于语言偏好的群体决策的软解法[J].系统工程学报,1996,11(4):53-60. 被引量:3
  • 4潘正君 康立山 等.演化算法[M].北京:清华大学出版社,1998..
  • 5任健林 施裕生.工程建设进度控制[M].北京:水利水电出版社,1993..
  • 6关柯.建筑施工手册(第三版)[M].北京:中国建筑工业出版社,1997..
  • 7运筹学编写组.运筹学[M].北京:清华大学出版社,1996..
  • 8袁子仁,网络法施工管理,1987年
  • 9袁子仁,网络计划模型与控制,1987年
  • 10何建坤,实用线性规划及计算机程序,1985年

共引文献52

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部