摘要
本文通过山区某工程桩基采用全套管振动取土施工工艺的工程实践,介绍了全套管振动取土灌注桩的施工工艺流程、存在问题及处理方法,工程检测和实践效果表明全套管振动取土灌注桩是一种发展潜力大、质量较高具有进一步研发和推广价值的环保桩型。
Through application of a mountain full of high - frequency vibration borrow piles of construction example, introduced a full set of high - frequency vibration borrow piles of construction process, construction difficulties and processing methods, and other large diameter piles contrast, the full set of high - frequency vibration is a pile borrow more advanced pile.
出处
《福建建筑》
2007年第12期67-68,74,共3页
Fujian Architecture & Construction
关键词
全套管
振动取土
灌注桩
高频液压振动锤
A full set of high - frequency vibration borrow pile high - frequency vibration hydraulic hammer High - power pump sand