摘要
以巴基斯坦巴罗塔工程C-03合同为背景,简述了在FIDIC施工合同条件(1999年版)下,承包商由于非自身原因提出延长工期索赔的合同依据,以及在延期索赔过程中应遵循的程序和原则。还介绍了承包商在巴罗塔C-03合同下成功地完成延长工期索赔的步骤,对时间索赔报告和费用索赔报告的编制原则和方法进行了总结。
On the basis of Pakistan Ghazi-Barotha Hydropower Project, Contract C-03 Power Complex and Auxiliary Works, this article briefly describes the contract terms and conditions under which the Contractor is entitled to claim Extension of Time for Completion as well as the procedure and principle to be complied with during the claim process under FIDIC Conditions of Contract for Construction (edition 1999). It also introduces the detailed steps by which the Contractorsuccessfully complete the claim for Exten- sion of Time for Completion of the Works under Contract C-03, and concludes the principle and method for the preparation of the Time Claim Report and Cost Claim Report in order to provide reference for other similar projects.
出处
《东方电气评论》
2007年第4期35-44,共10页
Dongfang Electric Review
关键词
FIDIC合同
工程延期
索赔报告
延误事件
基线计划
与时间相关的间接费用
FIDIC conditions of contract
extension of time for completion
claim report
delay event
baselineprogramme
indirect time-related cost