期刊文献+

乌江银盘水运枢纽最大通航流量 被引量:1

Maximum Navigation Discharge of Yinpan Hydro-junction in Wujiang River
下载PDF
导出
摘要 乌江银盘水运枢纽工程水头高36.5 m,由现行规范洪水频率法确定出的山区河流通航建筑物的最大通航流量标准过高。通过对洪水频率法的讨论及对山区河流通航建筑物最大通航流量确定方法的探讨,采用通航历时保证率法确定乌江银盘枢纽最大通航流量,得出的最大通航流量经济上合理,技术上可行。 The water head of Yinpan Hydro-junction project in Wujiang River is 36.5 m. At present, the maximum navigable discharge for the navigation structures in mountianous river specified by the flood frequency method of existing specification is too high. On the basis of analyzing the flood frequency method and the method of determining maximum navigation discharge for navigation structures in mountainous river, the maximum navigation discharge of Yinpan hydro-junction in Wujiang River was determined by the guarantee rate of navigable duration, the calculated maximum navigation discharge is reasonable economically and feasible technically.
作者 刘玲 赵志舟
机构地区 重庆交通大学
出处 《中国港湾建设》 北大核心 2007年第6期4-6,共3页 China Harbour Engineering
基金 西部交通建设科技项目(200532800030)
关键词 山区河流 最大通航流量 历时保证率 mountainous river maximum navigable discharge guarantee rate of duration
  • 相关文献

参考文献4

  • 1JTJ305-2001.船闸总体设计规范[S].[S].,..
  • 2谭先泽,刘彦,蹇依.嘉陵江航运梯级开发关键技术研究--山区河流船闸设计最高通航水位的研究[R].成都:四川交.通厅内河院,2003.
  • 3杨本新.枢纽通航建筑物最大通航流量设计标准探讨[J].人民长江,2004,35(10):24-26. 被引量:3
  • 4赵成生.重庆乌江银盘水电站枢纽布置及导流专题研究报告[R].武汉:长江水利委员会长江勘测规划设计研究院,2005.

共引文献118

同被引文献4

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部