摘要
1995年6~7月,成昆铁路蒲坝小龙滩沟5次暴发泥石流。因山前区古泥石流堆体“复活”补给了大量物质,酿成了成昆铁路近年较大的一处泥石流灾害。本文从降雨、河槽侵蚀机理等方面进行了成因探讨,并提出了以疏导工程防止泥石流改道、控制古堆体活动为主的整治对策。
In June and July, 1995, debris flow broke out for five times in Xiaolongtan Gully of Puba Basin. Because a large amount of materials were given by relapsing old debris flow sedimentin in fore mountain region, Chengdu Kunming Railway suffered a serious debris flow damage. The formation has been studied from railfall, river erosion mechanism and others in this paper. In order to prevent debris flow′s detour and control the activity of old sediment, the dredge project is presented as a major countermeasures.
出处
《中国地质灾害与防治学报》
CSCD
1997年第3期63-67,共5页
The Chinese Journal of Geological Hazard and Control
关键词
泥石流
铁路
河槽侵蚀机理
old debris flow sediment relapsing, river erosion mechanism, dredge project