结合松原龙华松花江特大桥的施工过程,介绍墩梁临时固结的措施,以及挂篮的细部构造及其各部件的功能,并对1#块悬臂浇注时,挂蓝的改进进行阐述。
Combined with the course of construction of Songyuan Longhua Songhua River super-sized bridge, methods of temporary anchor of beam and pier, structure and function of the form traveler, and improved structure for the pasret-hung easting of the 1 # pier base were introduced in this paper.