双代号网络图中虚工作时间参数计算的探讨 被引量:4

A Probe into the calcaulation of the time parameter of dummy activity in the activity-on-arrow network
下载PDF
导出
摘要 通过分析研究对把虚工作视同实工作进行其时间参数计算的观点提出质疑,得出计算双代号网络图各实工作时间参数时不要进行虚工作时间参数计算的结论,并指出何时进行虚工作时间参数计算会对其相关实工作时间参数产生影响。 This paper deeply analyze, and doubts about the view that dummy activity is eousiderd as normal activity to conduct the calculation of time parameter. The paper reaches the conclusion that the time parameters of dummy activity should not be included when calculating the time parameters of all the normal activities in activity-on-arrow network. It also points out the time when the calculation of the time parameter of dummy activity is conducted, during which the time parameter of the related activities will be affected.
作者 兰立华
出处 《山西建筑》 2008年第6期159-160,共2页 Shanxi Architecture
关键词 双代号网络 虚工作 时间参数 activity-on arrow network, dummy activity, time parameter
  • 相关文献

参考文献4

  • 1JGJ/T 121-99,网络图计算规范[S].
  • 2赵志缙,应惠清.建筑施工[M].上海:同济大学出版社,2003.
  • 3郭正兴,李金根.建筑施工[M].南京:东南大学出版社,2004.
  • 4田彦华,李海霞.全国监理工程师执业资格考试复习指导[M].天津:天津大学出版社,2002.

共引文献3

同被引文献11

引证文献4

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部