摘要
详细介绍了35 m预制小箱梁的预制工艺和安装施工技术。结合现场施工条件,对预制场地、台坐、箱梁定型组合钢模、混凝土施工等进行了施工优化,并加强夏季质量控制措施。箱梁的安装,采用了轨道平车运梁,架桥机吊装。施工上因地制宜,确保了箱梁施工质量。所提供的方法和措施,为类似工程提供借鉴和参考。
A detailed description is given of the technique for prefabrication and erection of the 35 m small box girder. In connection with the site conditions, the prefabrication yard, abutment, fixed composite steel form of the box girder and concreting are optimized with enhanced measures for quality control in summer. The box girder is conveyed with the rail cart and erected with the bridge erector. Construction measures are suited to local conditions to guarantee quality. The methods and measures are all for reference of similar works only.
出处
《中国市政工程》
2007年第A02期75-78,共4页
China Municipal Engineering
关键词
高架桥
小箱梁
预制
运输
吊装
viaduct
small box girder
prefabrication
transport
erection