摘要
分析了同煤钢铁公司450m3高炉炉况恶化的原因,详细介绍了对炉况恶化各阶段的处理情况。通过采取一系列措施,高炉逐步恢复正常。
Reasons of emergency of 450 m^3 BF was analyzed. Treatment situation of emergency in varied period was introduced in delail. The blast furnace conditions were gotten right by adopting a series of measures & Datong Coal Mine Group Iron & Steel Co. Ltd.
出处
《山西冶金》
CAS
2007年第6期39-41,共3页
Shanxi Metallurgy
关键词
炉料
炉况
高炉操作
blast furnace bruden, furnace condition, orperation