长梁山隧道F_(26)断层施工超前地质预报 被引量:2

Geological Prediction in F_(26) Fault Zone of Changliangshan Tunnel
下载PDF
导出
摘要 研究目的:在隧道施工中,准确预报施工前方地质条件,尤其是区域断层的规模、性质和影响范围,将影响施工质量、工期与安全。研究方法:在采用针对性地质调绘、掌子面素描、综合物探、水文长期观测等综合方法基础上,进行相关性分析。研究结果:采用节理相关性预报断层在洞内的出现里程位置,并推导出相关公式。研究结论:经施工验证F26断层采用的综合超前预报技术是合理的、有效的;运用节理相关性分析方法,预报了断层在洞内的出现里程位置;地质超前预报应针对地质特点,选取相应的预测预报技术。 Research purposes: During tunnel excavation procedure, the geological predictions in advance for the area in front the construction site, especially the prediction of scale, nature and influencing scope of the regional faults are very important to the construction quality, schedule and safety.Research methods:The relative analysis is made on the base of geological survey, working face sketch, comprehensive physical prospecting, long- term hydrologic observations and other comprehensive methods.Research results:The location of the fault in the tunnel can be predicted by adopting the relative joints nature, and the relating formulas are derived.Research conclusions:The construction practice shows the comprehensive prediction technology adopted in F26 fault zone is reasonable and effective. The fault location in tunnel is predicted by the method of joint relativity analysis. The different prediction technologies should be adopted according to the different geological conditions.
作者 辛民高
出处 《铁道工程学报》 EI 北大核心 2007年第12期14-18,共5页 Journal of Railway Engineering Society
关键词 区域断层 超前地质预报 信息化施工 regional fault geological prediction informationized construction
  • 相关文献

参考文献3

  • 1隧道施工开挖工作面前方不良地质预报[R].地质物探试验研究中心,1995.
  • 2梁彦忠.弹性波反射法在隧道施工超前预报中的应用[R].西安:铁道第一勘察设计院,1997.
  • 3中华人民共和国行业标准(2007.12.01实施送审中),铁路隧道超前地质预报技术指南(送审稿)[S].

同被引文献22

引证文献2

二级引证文献18

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部