摘要
针对成套打包采购的瓶颈是采购周期很长,根据不同种类零件采购提前期的差异进行分类,将原来进口套件中采购周期较长的零件拆分成较长提前期零件的套件(LongLead Time Kits,简称LLT套件),分别进行采购。并借助于数量统计,给出相应的安全库存的计算模型。达到缩短绝大部分零部件采购周期,降低库存总成本的目标。
Separating long lead time kits from current package kits BOM and creating a long lead time BOM and ordering them separately, the paper uses the knowledge of statistics to give a formula for safety stock so as to shortening the procurement cycle and lowering the inventory cost.
出处
《物流技术》
2008年第1期95-97,共3页
Logistics Technology
关键词
采购周期
LLT
安全库存
procurement cycle
long lead time kit
safety stock