控制空场嗣后一次充填质量的技术改进 被引量:5

Technique improvement to control the filling quality of open stope in one time
下载PDF
导出
摘要 充填接顶和采场脱水是应用充填采矿法的矿山急需解决的两个技术问题。结合某矿分段空场嗣后一次充填采矿法的多年实践,分析了充填接顶和采场脱水问题的产生原因,详细叙述了控制空场嗣后一次充填质量的改进技术。改进后,采场充填接顶率显著提高,充填采场基本无多余积水。改进技术对条件相似的矿山推广空场嗣后一次充填采矿法具有借鉴价值。 Roof-contacted filling and dehydration in stope are two critical problems in mines in which backfill mining method was used. Combining with several years experience on open stope backfill in one time, the causes of the problems were analyzed and some technique improvements were put forward. And then, the roof-contacted rate of filling was obviously enhanced; there was little seeper any more. It provides a good reference for similar mines.
出处 《黄金》 CAS 北大核心 2008年第2期22-25,共4页 Gold
基金 国家自然科学基金项目(50374066) 教育部"新世纪优秀人才支持计划"资助项目(NCET-05-0487) 教育部博士点基金项目(20070290513)
关键词 空场嗣后一次充填采矿法 充填接顶 采场脱水 backfill mining method of open stope in one time roof-contacted filling dehydration in stope
  • 相关文献

参考文献3

二级参考文献9

共引文献47

同被引文献31

引证文献5

二级引证文献23

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部