摘要
采用实例计算,指出在供电规划阶段,计算小区电力负荷,采用供电部门制定的电力负荷计算方法较之建设部门有关资料的计算方法大许多,由此造成小区变配电所装机容量过大。
Taking examples for calculation, it is pointed out that during power supply plan calculated figure of residence community electrical load according to methods proposed by ministry of power supply is greater than that by ministry of construction, installed capacity of substation in residence community become much more accordingly.
出处
《建筑电气》
2008年第2期11-13,共3页
Building Electricity
关键词
小区供电规划
电力负荷
需要系数
Power supply plan for residencecommunity Electrical load Demand factor