摘要
三峡二期工程大坝上下游面混凝土裂缝成因复杂,责任难以界定,且裂缝检查与处理项目工期紧、难度大、内容庞杂,施工单位索赔金额巨大。按责任划分及费用分担原则进行合理补偿,是解决此类复杂索赔问题的较好方式。做好现场签证,明确计量、计价原则,编制工程量清单,是确定大型、复杂变更项目补偿金额的基础。
The formation cause of concrete crevice on the upper&down stream clam surface of the three gorges project is complex, and who should bear the responsibility is difficult to precisely mark off. The survey and trealment project of the crevice has the chacracteristics of intense time limit, great difficulty and numerous items. The best way to solve this kind complex compensation issue is mutual shams on the basis of respomibility compartmentalization. The detailed attestation of engineer, specific principle of measure and quotation is the foundation to exactly confirm the compensation charge of complex project.