摘要
介绍了刘家峡水电厂#5机组扩修中采用GE公司方法——应用自动盘车装置进行轴线调整,确保了机组安装质量和轴线调整安全性。实践证明,该法省时、省力、操作简单、停点准确、轴系受轴向和径向干扰小、效率高、质量好。
This paper introduced automatic mechanical turning equipment for axial alignment of generating unit recommended by GE during extensive overhaul of Unit No. 3 in Lijiaxia Hydropower Station. This method guarantees installation quality and safety of axial alignment for generating unit. Practice shows that this method has following advantages :save of time and effort ;simple operation, high accuracy ;less radial and axial interference of shafting system ; high efficiency and quality.
出处
《水电能源科学》
2008年第1期160-163,共4页
Water Resources and Power
关键词
自动盘车装置
水轮发电机组
轴线调整
automatic mechanical turning equipment
hydroelectric generating units
axial alignment