大型输水渠道退水口的退水能力研究 被引量:6

Recession capacity of discharge outlet of large water transfer channels
下载PDF
导出
摘要 选取南水北调中线工程输水干渠中的澎河和澧河退水闸,采用一维非恒定计算软件,模拟计算各种紧急情况下干渠中的非恒定流态,对其退水能力进行分析和校核。结果表明:渠段两端闸门同时紧急关闭且退水闸不启用时,渠段中的水面会发生长时间的振荡。同时关闭草墩河和澎河节制闸以及该渠段间的分水口时,在设计流量下,即使不开启退水闸,也不会引起渠道漫溢;在加大流量的情况下,澎河退水闸和澧河退水闸必须同时启用至少3 h才能有效避免漫溢事故的发生。所关闭的两个节制闸间的渠段越长,退水闸运行的时间也越长。 With the Penghe and Lihe exit sluices in the main canal of the South-to-North Water Transfer Middle Route Project as examples, one-dimensional unsteady flow calculation software was adopted for simulating unsteady flow pattern in the main canal under different emergency conditions, and their recession capacities were analyzed and chocked. The result shows that large fluctuation of water surface occurs when the gates at two ends of the canal are closed suddenly and simultaneously with the exit sluices not open. When the Caodunhe and Penghe controlling gates and the diversion gate in this section are closed simultaneously, overflow phenomenon does not occur in the canal under the design flux even ff the exit sluices are closed. However, if the flux is increased, the overflow phenomenon can be avoided only if the two gates are opened for at least about 3 hours, and the longer the distance between two closed controlling gates, the mere the operating time of the exit sluices.
出处 《水利水电科技进展》 CSCD 北大核心 2008年第1期58-61,共4页 Advances in Science and Technology of Water Resources
基金 中国博士后科学基金(200603900078) 国家自然科学创新研究群体科学基金(50221903)
关键词 南水北调中线工程 输水干渠 非恒定流 退水口 渠道漫溢 水位振荡 main canal of South-to-North Water Transfer Middle Route Project unsteady flow discharge outlet overflow in canal water level fluctuation
  • 相关文献

参考文献9

二级参考文献15

  • 1丁志良,谈广鸣,陈立,舒彩文.输水渠道中闸门调节速度与水面线变化研究[J].南水北调与水利科技,2005,3(6):46-50. 被引量:26
  • 2怀特E B 清华大学流体传动与控制教研组(译).瞬变流[M].北京:水利电力出版社,1978..
  • 3麦赫默德K 林秉南(译).明渠不恒定流(第1卷)[M].北京:水利电力出版社,-..
  • 4文丹 吴泽宇.南水北调中线工程规划专题报告之二--供水调度与调蓄研究[M].水利部长江水利委员会,2001..
  • 5[3]Henry, H. R. "Discussion of Diffusion of submerged jets by M. L. Albertson, Y. B. Dai, R. A. Jensen, and H. Rouse."Transaction of ASCE, Vol. 115, 1950:687-694.
  • 6[4]Prabhata K. Swamee. Sluice-gate discharge equations[J]. Journal of Irrigation and Drainage Engineering, ASCE, 1992, Vol.118(1) :56-60.
  • 7[4]Swamee PK.Sluice-gate discharge equation[J].Journal of Irrigation and Drainage Engineering,ASCE,1992,118(1):56-60.
  • 8[5]Henry HR.Discussion of diffusion of submerged jets by M.L.Albertson,Y.B.Dai,R.A.Jensen,and H.Rouse[J].Transaction of ASCE,1950,115:687-694.
  • 9王长德,阮新建.南水北调中线总干渠控制运行设计[J].人民长江,1999,30(1):19-21. 被引量:12
  • 10周斌,吴泽宇.调水工程渠道运行控制方案设计[J].人民长江,1999,30(4):7-9. 被引量:6

共引文献48

同被引文献78

引证文献6

二级引证文献41

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部