摘要 结合重庆市在建大坪隧道的工程地质和设计情况,对隧道洞身Ⅲ类围岩地段采用不同施工方法锚喷初支开挖时的力学动态响应进行了数值模拟,分析了围岩应力场、应变场、位移场,以及锚喷时喷层、锚杆的力学性态,通过综合比较得出,台阶三分部法开挖是适合大坪隧道Ⅲ类围岩段合理的施工方法。 According to the design and geological condition of Da-ping tunnel, numerical methods used to analyze the mechanical responses of tunnel with large cross section on surrounding rock condition of class Ⅲ. Then stress field , meet an emergency field , displacement field and mechanical responses of shotcrete and bolt support of different construction methods are studied, and base on compare synthetically step three branch excavating method is the rational construction of Da-ping tunnel surrounding rock condition of class Ⅲ.
出处 《中国矿业》 北大核心 2008年第2期90-93,共4页 China Mining Magazine
基金 国家自然科学基金重点项目(No.50334060)资助课题
关键词 大断面隧道 施工方法 锚喷 数值模拟 tunnel with large cross section, construction method, shotcrete and bolt support, numerical simulation
  • 相关文献

参考文献9

二级参考文献26

共引文献337

同被引文献61

引证文献9

二级引证文献36

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部