600MW机组锅炉壁式再热器区域炉墙开孔施工中存在的难点分析 被引量:1

Analysis of Difficulty in Trepanning of Boiler Wall with Wall Type Reheaters of 600 MW Units
下载PDF
导出
摘要 针对广东国华粤电台山发电有限公司(以下简称台山电厂)600MW锅炉因燃用神华煤易结渣而造成过热器区域结渣、积灰较严重的现象,提出了在锅炉两侧墙各加装1台长杆蒸汽吹灰器的改进方案。为此,就加装长杆吹灰器的施工方案难点进行了分析,提出了改进意见,并成功实施了改造,这对燃用神华煤的大型锅炉的运行具有较大的指导意义。 The serious slagging of the Shenhua coal fired in 600 MW boilers of Guangdong Guohua Yudean Taishan Power Generation Co,, Ltd. resulted in severe slagging and ash deposition in the reheater region. To solve the problem, it was presented that a long-rod steam soot blower be added respectively on two walls of the boiler. Upon analysis of the difficulty in adding the soot blowers, some improving suggestions were put forward and the units modified successfully, which is of referential value to the operation of large boilers fuelled by Shenhua coal.
出处 《广东电力》 2008年第2期52-54,共3页 Guangdong Electric Power
关键词 锅炉 壁式再热器 结渣 积灰 吹灰器 boiler wall type reheater slagging ash deposition soot blower
  • 相关文献

参考文献2

  • 1DL/T748.2-2001,火力发电厂锅炉机组检修导则第2部分:锅炉本体检修[S].
  • 2上海锅炉厂.国华台电600MW机组锅炉图纸[R].上海:上海锅炉厂.

同被引文献2

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部