某炼钢厂房体量大,结构布置复杂,结合后续技术改造对主厂房结构及电炉平台进行了全面检测,对不满足规范要求或不利于技术改造的情况提出切实可行的处理建议。检测实践经验可供类似工程参考。
An overall detection of the main mill building structure for a steelmaking plant was carried out according to the technical reform, it was proposed that the feasible suggestions on conditions that could not meet the requirements of codes or those were not faverable for technical reform, The experience of the detection may be a reference for similar projects.
出处
《工业建筑》
CSCD
北大核心
2008年第2期103-105,共3页
Industrial Construction
关键词
厂房
检测
处理建议