摘要
在介绍宜兴抽水蓄能电站上库闸门井工程情况的基础上,介绍闸门井混凝土衬砌滑模施工中的垂直运输、钢筋绑扎固定、混凝土浇筑、滑体滑升及滑模控制等施工全过程。等截面结构混凝土衬砌工程采用滑模施工要比传统的支模施工更能保证质量,降低成本,提高工效,减少安全隐患。
The paper introduces the vertical transport 、the assembling reinforcement、the concrete pouring、the sliding body raising and the control of slipform of gate shaft in based on the introduction of gate shaft upstream reservoir of yixing pumped storage power station. The construction quality of slipform is better than the traditional method, the cost is lower, the efficiency is higher, the construction is safer.
出处
《东北水利水电》
2008年第3期52-53,共2页
Water Resources & Hydropower of Northeast China
关键词
闸门井
滑模施工
宜兴抽水蓄能电站
gate shaft
construction of slipform
yixin pumped storage power station.