结合唐钢司家营铁矿北区Ⅲ采场即将由露天开采转为地下开采的实际和N2-N4线间残留矿体的赋存状况,对残留矿体的回收方案进行了设计。
In light of the reality that No. 3 pit in north area of Sijiaying Iron Mine will proceed from open pit mining into underground mining and the occurrence of the residual orebody remaining between N2 and N4 lines, a scheme for recovering the residual orebody is designed.
出处
《金属矿山》
CAS
北大核心
2008年第3期35-37,共3页
Metal Mine
关键词
露天转地下开采
残矿回收
无底柱分段崩落法
Transition from open pit to underground mining, Recovery of residual orebody, Pillarless sublevel caving