摘要 模具电极加工的关键工序调度问题,可以近似采用具有CNC和EDM两道工序,且后工序带有成组特征的柔性流水车间调度模型进行描述。以实现最小化电极总拖期量为目标,建立了该问题的数学模型,提出了一种启发式算法来获取满意解,并应用实例验证了该算法的有效性。 Scheduling problems with the key processes of mould' s electrode, can be approximately described by the scheduling model of flexible flow shop with CNC and EDM processes, including group characteristic in the last process. To minimize the total tardiness of electrode, it established a mathematical model, and then presented a heuristic algorithm to get a satisfactory solution. The application example shows the effectiveness of the algorithm.
出处 《工业工程》 2008年第2期58-61,65,共5页 Industrial Engineering Journal
基金 国家自然科学基金资助项目(50675039) 省团队资助项目(5200197) 粤港招标资助项目(2005A10207002) 广州市科技攻关资助项目(2006Z2-D3021)
关键词 模具 柔性流水车间 成组调度 启发式算法 mould flexible flow shop (FFS) group scheduling heuristic algorithm
  • 相关文献

参考文献10

  • 1Salvador M S. A Solution of a special class of flow shop scheduling problems[ C] //Proceeding of the Symposium on the Theory of Scheduling and Its Applications, Berlin: Springer Verlag, 1973 : 83-91.
  • 2Gupta J N D. Two-stage hybrid flow shop scheduling problem[J]. J Opl Res Soc,1988,39(4) :359-364.
  • 3Wittrock R J. Scheduling alogorithms for flexible flow lines [ J]. IBM Journal of Research and Development, 1987,29 (4) :401-412.
  • 4Wittrock R J. An adaptbale scheduling algorithms for flexible flow lines[ J]. Opers Res, 1988,33 (4) :445-453.
  • 5Kuriyan K, Reklaitis G V. Scheduling network flowshops so as to minimize makespan [ J ]. Computers Chem Engng, 1987,13 (1/2) : 165-173.
  • 6Sriskandarajah C, Sethi S P. Scheduling algorithm for flexible flow shops : worst and average case erformance [ J ]. European Journal of Operational Research , 1989,43 (3) : 140-160.
  • 7Lee C Y, Vairaktarakis G L. Minimizing makespan in hybrid flow shops [J]. Operations Research Letters, 1994,16 ( 2 ) : 149-158.
  • 8王莉,王梦光.基于遗传算法的多机多阶段的Flow Shop问题[J].信息与控制,1997,26(4):296-300. 被引量:11
  • 9王莉,王梦光.基于准时制的零等待混合 Flow Shop 调度问题[J].东北大学学报(自然科学版),1998,19(4):349-351. 被引量:7
  • 10Rasaratnam Logendran, Sara Carson, Erik Hanson. Group scheduling in flexible flow shops [ J ]. Int J Production Economics ,2005,95 ( 3 ) : 143-145.

共引文献15

同被引文献57

  • 1熊禾根,李建军,孔建益,杨金堂,蒋国璋.考虑工序相关性的动态Job shop调度问题启发式算法[J].机械工程学报,2006,42(8):50-55. 被引量:33
  • 2王辉,鲁习文.工件带到达时间的两阶段柔性流水作业的近似算法[J].运筹学学报,2007,11(3):86-94. 被引量:3
  • 3GUPTA J, KRUGER K, LAUFF V, et al. Heuristics for hybrid flow shops with controllable processing times and assignable due dates[J]. Computers & Operations Research, 2002, 29(10): 1417-1439.
  • 4ALISANTOSO D, KHOO L P, J/ANG P Y. An immune algorithm approach to the scheduling of a flexible PCB flow shop[J]. International Journal of Advanced Manufacturing Technology, 2003, 22(11-12): 819-827.
  • 5LIN H T, LIAO C J. A case study in a two-stage hybrid flow shop with setup time and dedicated machines[J]. International Journal of Production Economics, 2003, 86(2): 133-143.
  • 6WANG W, HUNSUCKER L J. An evaluation of the CDS heuristic in flow shops with multiple processors[J]. Journal of the Chinese Institute of industrial Engineers, 2003, 20(3): 295-304.
  • 7ARTHANARI T S, RAMAMURTHY K G- An extension of two machines sequencing problem[J]. Opsearch, 1971, 8(1): 10-22.
  • 8SALVADOR M S. A solution to a special case of flow shop scheduling problems[M]. New York.. Springer. 1973.
  • 9GUPTA J N D. Two-stage, hybrid flowshop scheduling problem[J]. Journal of the Operational Research Society, 1988, 39(4): 359-364.
  • 10SHAUKAT A B, LUAN L L. Heuristics for scheduling in a flow shop with multiple processors[J]. European Journal of Operational Research, 1999, 113: 113-122.

引证文献4

二级引证文献15

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部