特高压黄河大跨越铁塔塔头吊装 被引量:25

Tower Head Hoisting and Installation for the UHV Transmission Line Yellow River Large Crossing
原文传递
导出
摘要 对特高压线路黄河大跨越铁塔塔头进行了分析,结合现有大跨越铁塔吊装设备,创新了吊装施工方法,在塔体上安装辅助抱杆,拓展了抱杆摇臂吊装范围;计算选定合适的节点和最佳的连接方式,将抱杆与塔体连为一体,达到稳定抱杆起吊性能、增加起吊能力的目的,实现了特高压黄河大跨越塔塔头吊装。 Analysis of tower head of UHV transmission line Yellow River large crossing is performed. Based on available hoisting and installation equipment innovative construction techniques that installs auxiliary lifting pole on tower body and extends pole ann hoisting range, are created. The appropriate nodes and optimum connection method are calculated to combine the lifting pole and tower together to stabilize the pole and increase its hoisting capability to realize tower head installation for the Yellow River large crossing.
出处 《电力建设》 2008年第4期20-23,共4页 Electric Power Construction
关键词 特高压 大跨越 铁塔 塔头 吊装 UHV large crossing transmission tower, tower head hoisting and installation
  • 相关文献

参考文献2

二级参考文献2

  • 1DL/T5154—2002.架空送电线路杆塔结构设计技术规定[S].[S].,..
  • 2李庆林.凌一朋,郭学闻.铝钢组合式抱杆中心压力试验及分析[A].超高压送变电施工技术信息网第十一届全网大会技术交流论文集[C],2005.10.

共引文献51

同被引文献90

引证文献25

二级引证文献77

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部