摘要
文章针对大唐信阳发电有限责任公司工程质量目标为确保鲁班奖,在前期策划中要求在保证混凝土内在质量和外部观感的同时,必须要有创新和不断提高施工工艺。因此,在烟囱工程施工中大胆采用了电动提升系统、烟囱大模板工艺等新技术和新工艺,经精心组织施工,努力做好细部处理,基本上达到了预期的效果。
Aiming at Datang Xinyang Power Generation Co. Ltd. project quality target for "Luban Award", during the early stage planning the renovation and continuously increasing construction technology should be executed in condition of ensuring the concrete internal quality and exterior impression. Therefore, in the process of stack construction new techniques and technologies are adopted, like motorized lifting, large stack pattern plates. Through careful construction organization and treatment in details the predicted results have been obtained in general.
出处
《电力建设》
2008年第4期72-74,共3页
Electric Power Construction
关键词
清水混凝土
大模板
电动提升系统
新技术
新工艺
as-cast concrete
large pattern plate
motorized lifting system
new technique
new technology