摘要
本文通过作者对工程实际经验的总结和有关标准规范的理解,对预应力钢筋混凝土管桩在施工过程中适用的施工方法及易出现的质量问题进行归纳、总结和分析,并提出一些合理的观点、方法。本文以锤击法(筒式柴油锤)为例进行探讨。
In the article, about the summary of the practical experience of the project and the understanding with normal standards, the authors conclude and analyze the quality problems and construction methods of the prestressed armored concrete cannular pilings that appear in the course of construction, and put forward some rational views and methods . This text carries on the discussion for the example with the method of hammer blow (sleeve diesel oil hammer ).
出处
《科技信息》
2008年第4期101-102,共2页
Science & Technology Information
关键词
预应力钢筋混凝土管桩
施工方法
质量保证
The prestressed armored concrete cannular pilings
Construction methods
Quality guarantee