太平峪抽水蓄能电站建设的经济评价分析 被引量:1

Evaluation and Analysis on Economic of construction of Taipingyu Pumped Storage Power Station
下载PDF
导出
摘要 针对陕西电网调峰形势日趋严重的现状,对建设陕西抽水蓄能电站进行探讨和论证也越发重要。本文针对太平峪抽水蓄能电站的特点,进行了相关的经济分析,并对其上网电价进行了初步探讨,为陕西电网建设实施提供了参考依据。 In view of more serious peak load regulation in Shaanxi power grid, it's more important to discuss and demonstrate the construction of pumped storage power station. Based on the characteristics of Taipingyu pumped storage power station, the relevant economic analysis is made and the onto-grid electricity rate of Taipingyu pumped storage power station is preliminarily discussed. It provides a reference for the construction of Shaanxi power grid.
作者 张昕
机构地区 陕西省电力公司
出处 《陕西电力》 2008年第3期78-80,共3页 Shanxi Electric Power
关键词 太平峪抽水蓄能电站 上网电价 经济评价 陕西电网建设 Taipingyu pumped storage power station onto-grid electricity rate evaluation and analysis on economic construction ofShaanxi power grid
  • 相关文献

参考文献5

  • 1[1]陕西电网建设太平峪抽水蓄能电站的必要性[R].西安:西北勘测设计院,2007.
  • 2[2]赴国网新源公司进行抽水蓄能电站建设管理及有关问题调研的报告[R].西安:西北勘测设计院,2007.
  • 3[3]陕西电网建设抽水蓄能电站的研究-经济分析报告[R].西安:西北勘测设计院,2007.
  • 4[4]太平峪抽水蓄能电站装机汇报材料[R].西安:西北勘测设计研究院.2007.
  • 5[5]太平峪抽水蓄能电站装机补充材料[R].西安:西北勘测设计院.2007.

同被引文献17

  • 1陈雪青,郑彤昕,石光,阮前途,高家芬,吴竹亭,陈开庸.有抽水蓄能电站的联合电力系统优化调度模型和算法[J].中国电机工程学报,1995,15(4):274-280. 被引量:16
  • 2言茂松,张少华,程道平,骆天华.抽水蓄能电站的系统建模及其应用[J].中国电机工程学报,1996,16(1):10-16. 被引量:1
  • 3丘文千.抽水蓄能电站运行优化的动态规划模型[J].水电自动化与大坝监测,2005,29(6):6-10. 被引量:19
  • 4Edgrado D. Castronuovo, Joao A. Pecas Lopes. Op- timal operation and hydro storage sizing of a wind- hydro power plant [J]. Electrical Power and Energy Systems, 2004, 26: 771-778.
  • 5Juan I. Perez-Diaz, Alejandro Perea and Jose R. Wilhelmi. Optimal short-term operation and sizing of pumped-storage power plants in systems with high penetration of wind energy [C]. Energy Market (EEM), 2010 7th International Conference on the European, 2010:1 - 6.
  • 6Gao Feng, Hallam Arne, Yu Chien-Ning. Wind gen- eration scheduling with pump storage unit by colloca- tion method [C]. Power I: Energy Society General Meeting, 2009. PESt09, IEEE, 2009: 1- 8.
  • 7Javier Garcia-Gonzalez, Rocio Moraga Ruiz de la Muela, Luz Matres Santos. Stochastic joint optimi-zation of wind generation and pumped~storage units in an electricity market[J]. IEEE Transactions on Power Systems, 2008, 23(2): 460- 468.
  • 8Bueno C, Carta J A. Technical-economic analysis of wind-powered pumped hydrostorage systems. Part Ⅱ.. model application to the island of E1 Hierro. Solar Energy 78, 2005:396 - 405.
  • 9Kazarils S A, Bakirtzis A G, Petridis V. A genetic algorithm solution to the unit commitment problem [J].IEEE Transactions on Power Systems, 1996, 11 (83 - 92) : 802 - 806.
  • 10张德旺.水电开发中如何评价高坝大库水电站的效益[J].华东电力,1985(5):48-51.